Initial Funding (2017)
Renew Atlanta Funding: $458,000
Park Pride Grant: $100,000
Little Five Alive & Don Bender: Raised $72,000 through brick sales for plaza
TOTAL: $630,000
City of Atlanta Bidding & Project Management
Jan 2019: Initial estimate from Renew Atlanta is $659,967.53.
Oct 2019: Renew Atlanta estimate rises to $880,000.
Dec 2019: Findley Plaza grouped with another Inman Park project to improve bidding process.
Feb 2020: Plaza grouped with a third project to reduce costs.
Apr 2020: Findley Plaza advertised with incomplete documents.
July 2020: Findley Plaza readvertised.
Oct 2020: Bids received in the amount of $1,171,046.70 and $1,033,425.98. Cost overruns in grading complete, mobilization, and traffic control add between $300k and $400k – all administrative costs that vendors add in for City bids.
Adjustments & New City Procurement Process
Oct 2020: City recommends open bidding process for more competitive bids.
Nov 2020: Pond works with the City of Atlanta to adjust bid documents.
Dec 2021: CIDs work with ADOT to create new CID Procurement Process.
CID Project
Management
Aug 2022: L5P CID enters into a Cooperative Agreement with the City.
March 2023: Park Pride takes back 2017 grant.
Jan 2024: L5P CID successfully manages Davis Plaza project as CID-P.
Feb 2024: L5P Alliance applies again and receives $100,000 Park Pride grant.
May 2024: L5P CID hires Pond & Co to manage the bidding and construction process.
Oct 2024: Pond prepares final bid package for City review.
Feb 2025: City approves bid package for posting.
Feb 2025: Pond & L5P Alliance post bid package online.
Mar 2025: Final bids received.
Apr 2025: Lichty Commercial Construction w/Russell Landscaping chosen as contractors.
May 2025: City Council creates new ordinance around tree recompense that triggers new process for permit approval through the Office of Buildings and City Arborist.
May 29: City signs off on permit and marks trees for removal.